How to Work with Us

Our Service Flow Chart

1. Quoting and DFM Consulting

Timeframe (Working Days)
1. DFM discussion: 5 to 10 days.
2. Quote days: 3 to 5 days.

Sends 2D/3D drawing with our Quote Requirement Form (QRF) for asking a quotation.

 

1. Engineering study your drawing with QRF.
2. Provides our Design for Manufacturability (DFM) suggestion or quote directly.

   

Proceeds with DFM discussion or approves the quotation.

 

2. Start Tooling Development

Timeframe (Working Days)
1. Design tooling: 7 days.
2. New tooling: 30 to 60 days.
3. Modifies existing tooling: 3 to 14 days.

Sends final 2D and 3D drawing for new tooling (or modify existing tooling). It will be better to have machining drawing and cosmetic requests.

 

Confirms tooling (or modifying) schedule and first article delivery date.

 

1. Designs tooling (or modifying) layout/drawing.
2. Sends to customer for approval.

 

Reviews and approves tooling (modifying) layout/drawing.

   

1. Proceeds with tooling (modifying) layout discussion.
2. Builds (or modify) tooling.

 

3. First Article / Sample Production

Timeframe (Working Days)
1. First sample delivery: 3-14 days.

Sends first casting/machining/finishing sample with QC inspection report.

 

1. Checks and Inspects our first production sample to determine if any minor modification is needed.
2. Approves first production sample.

 

1. Modifies tooling based on customer's feedback if needed.
2. Starts first batch production.

 

4. First Batch / Mass Production

Timeframe (Working Days)
1. First batch production samples: 14 to 21 days.
2. Mass production lead time: 30-45 days.

1. Examines first production batch and approves production quality.
2. Releases mass production order.

 

Receives and manufactures order for mass production and delivery.